PRELIMINARY — BID PHASE. This portal reflects Firm Foundations' proposed approach to FoJH Phase 2 while the bid remains under evaluation. Bid submitted 5:00 PM EST Friday, July 24, 2026. Award notification is expected on or before Wednesday, August 5, 2026. All content herein is provisional pending contract award and any addenda issued by the engineer.

Facility Improvements — Phase 2

Friends of Joshua House Foundation, Inc. | 1515 Michelin Court, Lutz, FL 33549 | AIA A101-2017
Phased Duration
~3 Months
Excluding Inspection Delays
Work Phases
4
Sequential (per RFI #001, Q10)
Bid Due
Jul 24
5:00 PM EST
Award By
Aug 5
Owner Notification
Funding
HUD CDBG
Federal · Davis-Bacon
Overall Progress
0%

Project Owner

Friends of Joshua House Foundation, Inc.
  • Tampa children's shelter — five homes on 11 acres
  • 1515 Michelin Court, Lutz, FL 33549 (project site)
  • Mailing: P.O. Box 2451, Lutz, FL 33548
  • (813) 406-5694 · friendsofjoshuahouse.org

Owner's Representative

InVision Advisors
  • Nathanael Moore — Owner's Rep · single point of contact
  • 1501 W. Cleveland Street, Suite 230, Tampa, FL 33618
  • (813) 435-0318
  • n.moore@invisionadvisors.com

Engineer of Record

Hendra & Associates, Inc.
  • Eric J. Hendra, PE — issues addenda & RFI responses
  • Plan set dated 12/5/23 (Phase 2 civil / site set)
  • Sheets referenced: C-001, C-003, C-100, C-102, C-500, C-501
  • Addenda deadline: July 10, 2026 · 5:00 PM

Contractor

Firm Foundations Asphalt & Concrete LLC
  • Arthur Wilmoth — Senior Project Manager
  • Joe Santerelli — Project Manager (Primary On-Site)
  • 10701 N Nebraska Ave, Tampa, FL 33612
  • 813-853-6597 · CBC1267421

Scope Summary

Civil / Site Work — behind Admin Building
  • Driveway (fire / access road) mill, repair & resurface
  • Retention ponds — excavation, edge-of-bank construction
  • Stormwater drainage — RCP, catch basins, inlets
  • Sidewalk repairs / replacement + ADA ramps & access aisles
  • Rock road / turf-block detail (pending engineer clarification)
  • Silt fencing, tree protection, erosion control (SWPPP)
  • 6′ security fencing (limits pending clarification)

Federal Compliance

HUD CDBG · Hillsborough County
  • Presidential EO 11246 — equal opportunity
  • Title VII, Civil Rights Act of 1964 (as amended)
  • Davis-Bacon Act — certified payroll, prevailing wages
  • Copeland Anti-Kickback Act
  • Section 3 — low-income hiring / contracting priority
  • Build America, Buy America (BABA) — iron, steel, mfg. products
  • E-Verify (F.S. 448.095) — all contractors & subs
DAVIS-BACON SECTION 3 BABA E-VERIFY EO 11246 2 CFR 200

Open RFIs — #001 Submitted July 2

Awaiting Engineer's Responses
  • Engineer's estimated quantities (pond CY / paving SF / RCP LF)
  • Fire road subgrade — silt, millings, roots, stump; borings?
  • Pond 2 trees at Building 3 corner (~12 trees, remove?)
  • Silt fencing / tree protection — full plan qty or Ph 2 limits?
  • Existing pump shed at top of bank — protection responsibility
  • Storm pipe conflicts — canopy, playground, sidewalk
  • ADA ramp vs. parallel stall striping conflict
  • Rock road detail vs. turf-block detail mismatch
  • Temporary facilities — portable toilets & handwashing
  • Proposed 4-phase / 3-month schedule approval
  • Owner-paid first round of materials testing
  • 6′ security fence — location & limits not shown
See RFI #001 (July 2, 2026) for the full text of each item and its plan reference.

MOT & Site Coordination

Active Children's Shelter Campus
  • Active residential campus — children on site daily
  • Work hours per HUD / owner: standard 7 AM – 5 PM weekdays
  • Playground & canopy stay accessible except during storm pipe work
  • Cones, barriers, spotters, backup alarms in every work zone
  • Full PPE (hardhats, hi-vis w/ FF logo, safety boots)
  • Daily site cleanup; drive lanes restored end of day
  • Section 3 & Davis-Bacon posters at staging area

Compliance Training — Pre-Con Workshop

Hillsborough County AHS · Davis-Bacon & Section 3
  • Section 3 benchmark: 25% of total labor hours by Section 3 workers; 5% by Targeted Section 3 workers (5% is inside the 25%)
  • Davis-Bacon: pay per Wage Determination for classifications actually performed — “Helper” is NOT an accepted classification
  • CWHSSA: 1.5× OT over 40 hrs; W&H can order back wages + liquidated damages
  • Copeland Anti-Kickback: certified payroll delivered within 7 days of the pay date
  • Records: preserve payrolls 3 years after prime contract completion
  • On-site postings: WH-1321 Davis-Bacon poster + Wage Determination + Section 3 + E-Verify (visible at all times)
  • Interviews: AHS will conduct on-site worker interviews — answers compared to certified payrolls
  • 1099s / independents: must be listed on the certified payroll
  • MBE/WBE: encouraged — 51%+ ownership disadvantaged / women
Full deck: Davis-Bacon & Section 3 Pre-Con Workshop (Rev 07.25.25) in Documents → Compliance

Post-Award Document Package

Per AHS Contractor Checklists
  • Before work starts: W-9 (prime + every sub), COI, SAM.gov registration, debarment certification, E-Verify certification, license verification (Sunbiz + DBPR), payroll signature authorization, HUD-4010 labor standard provisions in every subcontract
  • Weekly during work: Certified Payroll WH-347 with wet signature (prime + every sub, numbered sequentially) — Statement of Compliance (WH-347 page 2) — Section 3 Man Hour Report — “No Work” payroll submitted if no work
  • Monthly / periodic: HUD Form 2516 (contract/subcontract report) — Section 3 hiring updates — MBE/WBE participation tracking
  • Payment requests: AHS Payment Request Checklist attached to every draw
  • Any wage classification not on WD: SF-1444 request to AHS/DOL (30-day response minimum)
  • Any underpayment discovered: Restitution Affidavit + back-wage payment (interest per 26 U.S.C. 6621, compounded daily)
  • Closeout: Project Closeout Checklist (GC + all subs) · final payrolls · records preservation setup (3 yrs)
Full deck: forms + samples in Documents → Compliance once award is issued

Scope of Work — 4-Phase Approach

Sequenced per Firm Foundations' proposed phasing in RFI #001, Item 10 — back pond & rock road first (opens access), then drainage & basins, then the north road, then the south road. Target duration ~3 months, exclusive of inspection wait times. All phases contingent on engineer's written response to RFI #001 & any addenda.

Phase 1 — Back Pond + Rock Road

Behind Admin Building — Access & Retention
  • Install silt fencing & tree protection per C-003 (limits per RFI #4)
  • Selective clearing & tree removal at Pond 2 / Building 3 corner (~12 trees pending RFI #3)
  • Protect existing pump shed at top of bank (RFI #5 method TBD)
  • Pond 2 edge-of-bank excavation & grading per C-100 / C-501
  • Install rock road / turf-block per corrected detail (RFI #8)
  • SWPPP inlet protection in place before soil disturbance
Approx. duration: ~3 weeks · Opens rear access for the remainder of the work

Phase 2 — Drainage & Basins

Stormwater System — RCP & Structures
  • Install RCP storm pipe per C-102 (conflicts w/ canopy, playground, sidewalk — RFI #6)
  • Temporary removal & replacement of playground surfacing during pipe work
  • Sidewalk restoration where pipe crosses (RFI #6 confirms inclusion)
  • Catch basins, inlets, and structure grade rings
  • Regrade around basins to positive drainage
  • Materials testing round #1 (Owner-paid per RFI #11)
Approx. duration: ~3 weeks · Storm system energized before road paving

Phase 3 — North Road

Fire / Access Road — North Segment
  • Subgrade evaluation — undercut / stabilize per RFI #2 findings
  • Root pruning if required (tree fall responsibility per RFI #2)
  • Import & compact limerock base per FDOT spec
  • Prime coat + SP asphalt lift per plans
  • Sidewalk ramps installed with corrected ADA striping (RFI #7)
Approx. duration: ~3 weeks · Access maintained via south road

Phase 4 — South Road

Fire / Access Road — South Segment
  • Mirror of Phase 3 for the south segment
  • Sidewalk repairs / replacements & ADA warning surfaces
  • Final striping, wheel stops, ADA signage & signposts
  • Install 6′ security fencing per corrected limits (RFI #12)
  • SWPPP take-down and re-vegetation of disturbed areas
  • Punch list, site walk with Owner's Rep & Engineer
  • Certified payroll & Section 3 close-out reports to Owner
Approx. duration: ~3 weeks · Closeout, testing, as-built submission

Across Every Phase

Continuous Requirements
  • Certified payroll (Davis-Bacon) submitted weekly
  • Section 3 employment tracking & reporting (24 CFR Part 75)
  • BABA compliance documentation for iron, steel, mfg. products
  • E-Verify records for every worker on site (F.S. 448.095)
  • Daily sign-in sheets & toolbox safety talks
  • SWPPP inspections after every 0.5″+ rain event
  • Portable toilets & handwashing (pending RFI #9)
Every worker, every phase, every payroll cycle.

Exclusions & Assumptions

Pending Engineer Clarification
  • Assumes Owner pays first round of materials testing (per RFI #11)
  • Assumes ~12 Pond 2 trees are approved for removal (RFI #3)
  • Assumes engineer confirms turf-block IS the rock road detail (RFI #8)
  • Assumes silt fencing scope stops at Ph 2 work limits (RFI #4)
  • Basis-of-payment for unsuitable subgrade to be established (RFI #2)
  • Playground surfacing restoration approach TBD (RFI #6)
Bid pricing to be revised once RFI #001 is answered.

Proposed Schedule

📅
Bid Due: July 24, 2026 · 5:00 PM EST — Award By: August 5, 2026
Following award & NTP, FF requests ~2 weeks to submit certified payroll setup, order materials (RCP, stone, asphalt), and mobilize. The 12-week schedule below runs Phase 1 → 4 sequentially per RFI #001 Q10. Any duration change from RFI answers or addenda will be reflected here after review.
Phased Duration
~12 Wks
~3 Months Total
Active Phases
4
Sequential
Per-Phase Avg
3 Wks
15 Work Days
Mobilize After NTP
~2 Wks
Material Lead Time
Inspection Buffer
Excluded
Not in Duration
Phase / Activity Wks Phase 1 Phase 2 Phase 3 Phase 4
W1W2W3 W4W5W6 W7W8W9 W10W11W12
PHASE 1 — BACK POND + ROCK ROAD
SWPPP + Tree Protection Install1
Clearing / Tree Removal (Pond 2)1
Pond 2 Edge-of-Bank Excavation2
Rock Road / Turf Block Install1
PHASE 2 — DRAINAGE & BASINS
RCP Storm Pipe (C-102 route)2
Playground / Sidewalk Restore1
Catch Basins & Inlet Structures1
Materials Testing Round 1
PHASE 3 — NORTH ROAD
Subgrade Evaluation / Undercut1
Limerock Base + Compaction1
Prime Coat + SP Asphalt Pave1
Sidewalk Ramps + ADA Striping1
PHASE 4 — SOUTH ROAD + CLOSEOUT
South Road Subgrade + Base1
South Road Pave + Sidewalks1
Striping, Wheel Stops, ADA Signs1
6′ Security Fencing Install1
SWPPP Take-Down + Punch List1
Certified Payroll & Section 3 (Weekly)
SWPPP / Erosion
Drainage / RCP
Concrete / ADA
Grading / Base
Demo / Clearing
Paving
Striping
Payroll / Section 3
Inspection / Testing

Photo Timeline

Pre-bid site walk documentation and, following award, before / during / after documentation. Admin uploads from the Admin panel.

📷

No photos yet

Site walk photos from June 26 and, once awarded, construction progress photos will appear here.

Project Documents

Bid documents, RFI #001, plans, specifications, Davis-Bacon wage determinations, Section 3 forms, certified payrolls, sign-in sheets, safety meeting notes, and SWPPP inspection reports. Admin uploads from the Admin panel.

📂

No documents uploaded yet

Bid packet + RFI #001 will be uploaded once the site goes live.

Project Progress

Overall Completion0%
Phase 1 — Back Pond & Rock Road
0%
Phase 2 — Drainage & Basins
0%
Phase 3 — North Road
0%
Phase 4 — South Road & Closeout
0%
🚧

Bid pending — no updates yet

Progress updates will begin once the contract is awarded and Notice to Proceed is issued.

Field Notes

Observations, issues, RFIs, daily logs — added during construction via the Admin panel.

📝

No field notes yet

Admin Panel

Post Progress Update

📷

Click or drag photos here

📂 Upload Document

Sign-in sheets, safety meetings, SWPPP inspections, certified payrolls, Section 3 reports, RFI responses, addenda, plan revisions. PDFs preferred; PNG/JPG/DOC also accepted.

📂

Click or drag file here (PDF, image, or Office doc)

🗂 Manage Documents

View or delete uploaded documents.

No documents uploaded yet.

📷 Upload Photos

Up to 5 photos at a time. Auto-compressed for fast upload from phone.

📈 Update Progress

📝 Add Field Note

📝 Manage Field Notes

No field notes yet.

🗒 Manage Updates

No updates posted yet.